Superdry Basildon
RetailThis was the first Superdry store and was completed in 7 weeks. There was a very quick learning curve for this project understanding how Superdry wanted things like details of their steelwork fixings to how and the ligthing containment. The works within Basildons Eastgate shopping centre included new oak and sheet metal cladding, steel columns, brick slips, screeded and oak flooring, free standing shopfittings, ceilings, AC, lighting, data stockroom and decorations.
- Sector: Retail
- Duration: Eight Weeks
- Value: £200k
- Architect: Superdry
- Cost Consultant: Superdry